Construction report, 9 Dec 2025

Construction report Time Square 7 2025-12-09 · date from document content Original: EN 33 pp.

A newer version exists: Construction report, 28 Feb 2026

Summary

B2 slab complete; lift core 45%; B1 slab 35%, columns 20%, retaining wall 50%.

Key facts

B2 slab 100%Lift core 45%B1 slab 35%B1 retaining wall 50%