Construction report, 28 Feb 2026

Construction report Time Square 7 2026-02-28 · date from document content Original: EN 40 pp.

A newer version exists: Construction report, 9 Mar 2026

Summary

Above ground: 2F lift core done, 3F core 40%, 3F columns 25%, 4F slab 20%.

Key facts

2F lift core 100%3F lift core 40%4F slab 20%