Construction report, 29 Nov 2025
A newer version exists: Construction report, 9 Dec 2025
Summary
Temporary I-beam bracing removed; B2 slab 30%; lift-core walls started (5%).
Key facts
Bracing removal 100%B2 slab 30%Lift core 5%