Construction report, 9 Aug 2026
Summary
Excavation 97% (3rd layer to −9.5 m), pile caps 75%, PC4 cast; PC2 and tanks scheduled for mid-August.
Key facts
Excavation 97%Pile caps 75%−9.5 m level