Construction report, 29 Sep 2026
Construction report Time Square 10 Ocean View 2026-09-29 · date from document content Original: EN 18 pp.
Summary
Pile-head breaking 164 of 197 (83%); pile caps 20 of 28 (71%); grounding system installed.
Key facts
Pile heads broken 164/197 (83%)Pile caps 20/28 (71%)