Construction report, 19 May 2026
Construction report Time Square 10 Ocean View 2026-05-19 · date from document content Original: EN 23 pp.
A newer version exists: Construction report, 29 Sep 2026
Summary
Bored piles 159 of 197 (81%); sonic integrity tests 40%.
Key facts
Bored piles 159/197 (81%)Sonic tests 40%
Download PDF 7.5 MB
Originals are kept off the site; web copies are compressed.