Construction report, 9 Aug 2026

Construction report Time Castle XI 2026-08-09 · date from document content Original: EN 14 pp.

A newer version exists: Construction report, 29 Aug 2026

Summary

All 168 contiguous bored piles complete; main piles 2 of 25; sonic testing started.

Key facts

CBP piles 168/168Main piles 2/25
Download PDF 12.9 MB